Planned Metrorail Track Work
Metro has transitioned to a new program of preventive maintenance and planned capital work. Overnight and weekend hours will be used for enhanced preventive maintenance including cable testing to prevent smoke and fire incidents, stray current testing, trackbed cleaning, switch maintenance, torqueing (tightening fasteners, joint nuts and bolts) to eliminate excessive strain on infrastructure, and track geometry work to ensure the correct rail alignment.
NOTE: Every effort will be made to adhere to the schedule below. However, changes may be necessary due to weather, construction delays and other factors outside our control. This page will be updated as necessary.
For details about this weekend's track work, including minor projects that may impact your trip, view wmata.com/weekend.
| Start | End | Line | Impact | Stations Closed | Work Performed |
|---|---|---|---|---|---|
| Feb 7 | Feb 8 |
|
Trains single track between Dupont Circle and Van Ness | None | Safety walk and concrete repair and leak mitigation |
| Feb 7 | Feb 8 |
|
Trains single track between Anacostia and Navy Yard | None | Grout pad rehabilitation |
| Feb 9 | Feb 12 |
|
After 10 p.m., trains single track between Silver Spring and Forest Glen | None | Tunnel leak mitigation |
| Feb 14 | Feb 16 |
|
Trains single track between Silver Spring and Forest Glen | None | Tunnel leak mitigation |
| Feb 14 | Feb 16 |
|
Free shuttle buses replace trains between National Airport and Pentagon City | Crystal City | Crystal City new mezzanine project |
| Feb 21 | Feb 22 |
|
Trains single track between Dupont Circle and Van Ness | None | Safety walk and concrete repair and leak mitigation |
| Feb 21 | Feb 22 |
|
Free shuttle buses replace trains between National Airport and Pentagon City | Crystal City | Crystal City new mezzanine project |
| Feb 28 | Mar 1 |
|
Free shuttle buses replace trains between National Airport and Pentagon City | Crystal City | Crystal City second entrance construction |
| Feb 28 | Mar 1 |
|
Trains single track between Dupont Circle and Van Ness | None | Grout pad rehabilitation |
| Mar 7 | Mar 8 |
|
Free shuttle buses replace trains between Potomac Yard and Pentagon City | Crystal City, Reagan National Airport | Crystal City second entrance construction |
| Mar 14 | Mar 15 |
|
Trains single track between L'Enfant Plaza and Navy Yard | None | Grout pad rehabilitation |
| Apr 6 | Apr 10 |
|
After 10 p.m., trains single track between Friendship Heights and Van Ness | None | Tunnel leak repair |
| Apr 13 | Apr 17 |
|
After 10 p.m., trains single track between Friendship Heights and Van Ness | None | Tunnel leak repair |
| Apr 18 | Apr 19 |
|
Trains single track between Silver Spring and Forest Glen | None | Tunnel leak mitigation |
| Apr 18 | Apr 19 |
|
Trains single track between Ballston and Clarendon | None | Platform edge lighting |
| Apr 20 | Apr 24 |
|
After 10 p.m., trains single track between Friendship Heights and Van Ness | None | Tunnel leak repair |
| Jul 6 | Sep 6 |
|
Free shuttle buses replace trains between Friendship Heights and North Bethesda | Grosvenor-Strathmore, Medical Center, Bethesda | Purple Line Project, platform rehabilitation, aerial structure replacement |
| Start | End | Line |
|---|---|---|
| Feb 7 | Feb 8 |
|
| Impact | ||
| Trains single track between Dupont Circle and Van Ness | ||
| Stations Closed | Work Performed | |
| None | Safety walk and concrete repair and leak mitigation | |
| Start | End | Line |
|---|---|---|
| Feb 7 | Feb 8 |
|
| Impact | ||
| Trains single track between Anacostia and Navy Yard | ||
| Stations Closed | Work Performed | |
| None | Grout pad rehabilitation | |
| Start | End | Line |
|---|---|---|
| Feb 9 | Feb 12 |
|
| Impact | ||
| After 10 p.m., trains single track between Silver Spring and Forest Glen | ||
| Stations Closed | Work Performed | |
| None | Tunnel leak mitigation | |
| Start | End | Line |
|---|---|---|
| Feb 14 | Feb 16 |
|
| Impact | ||
| Trains single track between Silver Spring and Forest Glen | ||
| Stations Closed | Work Performed | |
| None | Tunnel leak mitigation | |
| Start | End | Line |
|---|---|---|
| Feb 14 | Feb 16 |
|
| Impact | ||
| Free shuttle buses replace trains between National Airport and Pentagon City | ||
| Stations Closed | Work Performed | |
| Crystal City | Crystal City new mezzanine project | |
| Start | End | Line |
|---|---|---|
| Feb 21 | Feb 22 |
|
| Impact | ||
| Trains single track between Dupont Circle and Van Ness | ||
| Stations Closed | Work Performed | |
| None | Safety walk and concrete repair and leak mitigation | |
| Start | End | Line |
|---|---|---|
| Feb 21 | Feb 22 |
|
| Impact | ||
| Free shuttle buses replace trains between National Airport and Pentagon City | ||
| Stations Closed | Work Performed | |
| Crystal City | Crystal City new mezzanine project | |
| Start | End | Line |
|---|---|---|
| Feb 28 | Mar 1 |
|
| Impact | ||
| Free shuttle buses replace trains between National Airport and Pentagon City | ||
| Stations Closed | Work Performed | |
| Crystal City | Crystal City second entrance construction | |
| Start | End | Line |
|---|---|---|
| Feb 28 | Mar 1 |
|
| Impact | ||
| Trains single track between Dupont Circle and Van Ness | ||
| Stations Closed | Work Performed | |
| None | Grout pad rehabilitation | |
| Start | End | Line |
|---|---|---|
| Mar 7 | Mar 8 |
|
| Impact | ||
| Free shuttle buses replace trains between Potomac Yard and Pentagon City | ||
| Stations Closed | Work Performed | |
| Crystal City, Reagan National Airport | Crystal City second entrance construction | |
| Start | End | Line |
|---|---|---|
| Mar 14 | Mar 15 |
|
| Impact | ||
| Trains single track between L'Enfant Plaza and Navy Yard | ||
| Stations Closed | Work Performed | |
| None | Grout pad rehabilitation | |
| Start | End | Line |
|---|---|---|
| Apr 6 | Apr 10 |
|
| Impact | ||
| After 10 p.m., trains single track between Friendship Heights and Van Ness | ||
| Stations Closed | Work Performed | |
| None | Tunnel leak repair | |
| Start | End | Line |
|---|---|---|
| Apr 13 | Apr 17 |
|
| Impact | ||
| After 10 p.m., trains single track between Friendship Heights and Van Ness | ||
| Stations Closed | Work Performed | |
| None | Tunnel leak repair | |
| Start | End | Line |
|---|---|---|
| Apr 18 | Apr 19 |
|
| Impact | ||
| Trains single track between Silver Spring and Forest Glen | ||
| Stations Closed | Work Performed | |
| None | Tunnel leak mitigation | |
| Start | End | Line |
|---|---|---|
| Apr 18 | Apr 19 |
|
| Impact | ||
| Trains single track between Ballston and Clarendon | ||
| Stations Closed | Work Performed | |
| None | Platform edge lighting | |
| Start | End | Line |
|---|---|---|
| Apr 20 | Apr 24 |
|
| Impact | ||
| After 10 p.m., trains single track between Friendship Heights and Van Ness | ||
| Stations Closed | Work Performed | |
| None | Tunnel leak repair | |
| Start | End | Line |
|---|---|---|
| Jul 6 | Sep 6 |
|
| Impact | ||
| Free shuttle buses replace trains between Friendship Heights and North Bethesda | ||
| Stations Closed | Work Performed | |
| Grosvenor-Strathmore, Medical Center, Bethesda | Purple Line Project, platform rehabilitation, aerial structure replacement | |